Mumbai Water Supply Gets Major Boost as BMC Speeds Up 2,000 MLD Water Treatment Plant and Pumping Station in Bhandup

Mumbai is moving closer to strengthening its long-term water supply as the Brihanmumbai Municipal Corporation (BMC) accelerates construction of a new 2,000 million litres per day (MLD) water treatment plant and a matching-capacity pumping station at Bhandup. The major infrastructure projects aim to meet the city's growing water needs and improve its water supply capacity for the future.

Construction work is progressing steadily at both sites, with significant progress reported in excavation and other key activities. Additional Municipal Commissioner (Projects) Abhijit Bangar has directed officials and contractors to speed up the work and complete the projects ahead of schedule.

BMC Reviews Progress of Bhandup Water Infrastructure Projects

During a recent inspection, Abhijit Bangar reviewed the progress of civil construction, electrical installations, mechanical systems and water treatment-related activities. He emphasized the importance of better coordination between departments, regular progress monitoring and quick action to resolve construction-related challenges.

He also instructed the agencies involved to deploy additional workers and machinery wherever required to maintain construction speed and meet project deadlines.

The Bhandup Complex is already one of Asia's largest water treatment facilities, with a combined treatment capacity of 2,810 MLD. It currently operates through two treatment units with capacities of 1,910 MLD and 900 MLD.

The proposed 2,000 MLD treatment plant will significantly expand this capacity and help Mumbai prepare for increasing water demand.

2,000 MLD Water Treatment Plant Reaches 16-Metre Excavation Depth

Excavation work for the new water treatment plant has reached a depth of 16 metres across an area of approximately six hectares. The project team is working to complete the remaining excavation by May 31, 2027.

Bangar has directed officials to ensure proper transportation and disposal of excavated soil and debris while maintaining construction progress.

The new treatment facility will include several advanced water purification and processing systems. These include Actiflo technology, Chlorination Contact Tank, Flow Splitter, Dual Media Filters, Backwash System, Actidyn process and wastewater pumping arrangements.

To avoid delays, officials have also been instructed to carry out Plain Cement Concrete (PCC), electrical installation and boundary wall construction alongside excavation activities.

Bhandup 2,000 MLD Pumping Station Nears Excavation Completion

Construction of the matching-capacity pumping station is also making good progress. Out of the planned excavation depth of 20.5 metres, approximately 18 metres have already been completed.

Excavation work for the bypass line, rising main and pump house building has been fully completed. Meanwhile, construction activities for the inlet chamber and clear water pumping sump have reached approximately 85% completion.

The concreting work for all 179 micropiles has also been completed, marking another important step in the project's progress.

During the review, Bangar instructed officials to establish clear deadlines for every stage of construction. He also emphasized that electrical installations should progress alongside civil construction instead of waiting for the completion of individual construction stages.

Additional manpower and resources have also been recommended to ensure faster execution.

How the New Bhandup Projects Will Benefit Mumbai

The two major infrastructure projects are expected to strengthen Mumbai's water supply network and support its future requirements as the city's population continues to grow.

With an additional treatment capacity of 2,000 MLD and a matching-capacity pumping station, the BMC aims to improve the city's ability to treat and distribute water efficiently.

The ongoing work at Bhandup represents an important investment in Mumbai's essential civic infrastructure. Faster construction, modern treatment technology and improved pumping facilities will help strengthen the city's long-term water management system.